We put into operation the Autotransformer АТДТН-200000/330/110-У1 on 330 kV SS Rivne. This substation belongs to the Zakhidna Power System of NEC Ukrenergo.
It should be noted that the technical re-equipment was carried out in the conditions of the existing energy facility.
Project start: | 2019 |
Project status: | Completed |
Project completion: | 2019 |
Types of works: | Electrical installation |
Commissioning | |
From September to December 2019, the following main works were performed:
– replacement of autotransformer АТ-2 АТДЦТН-200000/330/110У1;
– installation of current transformers in the circuit of the 110 kV switch of connection “AT-2” (link №8C at the 110 kV VRU);
– construction of a valve switching chamber and a new dry pipe installation AT-2;
– technical re-equipment of the 10 kV bus bridge;
– dismantling of existing equipment.
– installation of surge arresters to protect AT-2 at a voltage of 10 kV;
– replacement of AT-2 protections.
Kyiv Energy Construction Company Kyiv Energy Construction Company is a leading Ukrainian company providing engineering, procurement and construction (EPC) services for large-scale energy and industrial objects.
01013, 4A Promyslova Str.
General enquires
General enquires
We will get back to you soon