Current
Production report for Zaporizhzhia Nuclear Power Station

Kyiv Energy Construction Company performs works for Zaporizhzhia Nuclear Power Station

News
Current
Production report about works performed for Kaniv HPP – August 2021

Production report about works performed by Kyiv Energy Construction Company for Kaniv HPP during July-August 2021

News
Rehabilitation of 750 kV SS “Zaporizka” – production report for August 2021

Project “Rehabilitation of 750 kV, 330 kV outdoor switchgears, 150; 35; 15,75 kV equipment and auxiliaries at 750 kV SS “Zaporizka”

News
Current
Production report about works performed for Dnistrovska PSPP

Production report about works performed for Dnistrovska PSPP as part of the
project "Building works on the construction of the second stage of
Dnistrovska PSPP consisting of the hydroelectric unit No.4".

News
Production report about works performed for Kaniv HPP – June 2021

Production report about works performed by Kyiv Energy Construction Company for Kaniv HPP during May-June 2021

News
Summer meeting of the qualification board took place

At the Company the qualification board is held twice a year, in February and July. The latest meeting took place on July 23.

News
Current
Production report about works performed for Dnister Pumped Storage Hydroelectric Power Plant – June 2021

Agreement No. 01-10/2017 dated May 10, 2018 "Building works on the construction of the second stage of Dnistrovska PSPP consisting of
the hydroelectric unit No. 4 of the branch "Directorate of Dnistrovska PSPP construction" of PJSC "Ukrhydroenergo"

News
Current
Rehabilitation of 750 kV SS “Zaporizka” – production report for June 2021

Project “Rehabilitation of 750 kV, 330 kV outdoor switchgears, 150; 35; 15,75 kV equipment and auxiliaries at 750 kV SS “Zaporizka”

News
Production report about works performed for Kaniv HPP during March – April 2021

Production report about works performed by LLC “KECC” for Kaniv HPP during March 2021 – April 2021

News
Rehabilitation of 750 kV SS “Zaporizka” – production report for April 2021

Project “Rehabilitation of 750 kV, 330 kV outdoor switchgears, 150; 35; 15,75 kV equipment
and auxiliaries at 750 kV SS “Zaporizka”

News
Production report about works performed for Kaniv HPP

Reconstruction.  Electrical installation and commissioning works of Kaniv HPP. February 2021

News
Rehabilitation of 750 kV SS “Zaporizka” – production report

Project “Rehabilitation of 750 kV, 330 kV outdoor switchgears, 150; 35; 15,75 kV equipment
and auxiliaries at 750 kV SS “Zaporizka”

News
Bays No.8-9 of 330kV GIS at Dnistrovska PSPP have been energized

Installation works are currently continuing on the hydroelectric unit No. 4 of Dnistrovska PSPP.

News
Production report about works performed for Zaporizhzhia Nuclear Power Station – February 2021

We report about the works performed at the Zaporizhzhia NPP.

News
LLC “KECC” has concluded a design works contract for the data-center at Rivne NPP

According to the results of the public tender in “Prozorro” system, the contract for performance of design works on the “Construction of the data-center at Rivne NPP” facility was concluded between LLC “KECC” and SS “Rivne NPP” of SE “NNEGC “Energoatom” on February 12, 2021.

News
Current
Production report about works performed for Dnister Pumped Storage Hydroelectric Power Plant – February 2021

Status report for February. Object - Dnister Pumped Storage Hydroelectric Power Plant

Contact us
all contacts
Kyiv, Ukraine

01013, 4A Promyslova Str.

(044) 545-71-24

General enquires

mail@kebk.com.ua

General enquires

browse map
You can contact us directly
open the contact form