Gas piston cogeneration plant with a capacity of 4.5 MW

Деталізація

LLC “KEBK” has begun the implementation of the project “”Gas piston cogeneration plant””

 

The project provides for the installation of three cogeneration gas piston plants with a total capacity of 4.5 MW (1.5 MW each).

Year of start of work:

2025

Status of work:

Completed

Date of completion:

2025

Type of work:

Equipment supply

Electrical installation work

Complex of design works

Equipment installation

Construction work

2025

or use keyboard

As of now, a set of preparatory works has been completed, namely:

 

A geodetic layout of the construction site has been carried out;

 

A temporary access road has been constructed;

 

The construction area has been planned.

 

In addition, excavation work has begun to prepare the pits for the foundations of the cogeneration plants, and the equipment has been delivered and unloaded to the construction site.

Contact us
all contacts
Kyiv, Ukraine

01013, 4A Promyslova Str.

(044) 545-71-24

General enquires

mail@kebk.com.ua

General enquires

browse map
You can contact us directly
open the contact form