750 kV SS “Vinnytska”

Details

Reconstruction of 750 kV SWYD at 750 kV SS “Vinnytska”, shunting reactor’s bay ShR-750 “Zakhidnoukrainska”. Reconstruction 750 kV SWYD at 750 kV SS “Vinnitskaya”, bay of 750 kV OHL “Zapadnoukrainskaya”, including replacement of voltage transformers, line traps

 

Project start: 2016
Project status: Completed
Project completion: 2016
Types of work: Electrical installation
Commissioning
Construction

June 2016

or use keyboard

Employer: SE “NPC “Ukrenergo”, separated division “Pivdenno – Zakhidna PS.
Scope of Work: The set of construction, and installation-setup works at 750 kV SS “Vinnytska” on replacement of 2 phases of 750 kV shunting reactors and 3 phases of 750 kV surge arrestors in 750 kV reactor bay “Zakhidnoukrainska”.
Date of the Contract signing: 17.03.2016.
Commencement of works: April 13, 2016
Completion of works: June 26, 2016
The set of construction, installation and installation-setup works, including supply of equipment for the facility, includes the following reconstruction:
The existing equipment of 750 kV SWYD was dismantled and the following equipment was installed:
-Shunting reactor ROM-110000/750 type – 2 pcs.;
-Surge arrestors 3EP3 612-5PK54-2NE1 type – 3 phases.
-35 kV post insulators of the fourth beam of shunting reactors – 2 pcs.
Dismantlement and installation of existent oil-drip pots – 2 pcs. Installation of foundations (2 pcs.) and metal posts (2 pcs.) for 35 kV post insulators. Extension of one fire protection subwall between phases “B” and “C” of the reactors. Installation of cabling and wiring products. Installation of cubicle for power supply of welding equipment YaK-4 type (1 pc.) and YRP-100 type (1 pc.). Earthing of the installed equipment. Execution of commissioning works.

As of 26.06.2016, the equipment of 750 kV SWYD had been put into operation in full scope. Employer: SE “NPC “Ukrenergo”, separated division “Pivdenno-Zakhidna PS”.
Scope of Work: The set of construction, and installation-setup works at 750 kV SS “Vinnytska” on reconstruction of 750 kV SWYD “Vinnytska”, bay of 750 kV OHL “Zakhidnoukrainska”, including replacement of voltage transformers and line traps.
Date of the Contract signing: 29.03.2016.
Commencement of works: June 13, 2016
Completion of works: July 30, 2016
The set of construction, and installation-setup works, including supply of equipment for the facility, includes the following reconstruction:
The existing equipment of 750 kV SWYD was dismantled and the following equipment was installed:
-Voltage transformer TEIMF 765 type -3 phases;
-Line trap LPT 1/2000/40 type – 4 pcs.
-External installation cubicle for voltage transformer terminals -1 pc.
-750 kV voltage transformer West. Ukr. secondary circuits cubicle – 1 pc.
Installation of foundations (3 pcs.) and metal posts (3 pcs.) for 750 kV voltage transformer. Installation of cabling and wiring products. Earthing of the installed equipment. Execution of commissioning works.

As of 30.07.2016, the equipment of 750 kV SWYD had been put into operation in full scope.

Kyiv Energy Construction Company Kyiv Energy Construction Company is a leading Ukrainian company providing engineering, procurement and construction (EPC) services for large-scale energy and industrial objects.

Contact us
all contacts
Kyiv, Ukraine

01013, 4A Promyslova Str.

(044) 545-71-24

General enquires

mail@kebk.com.ua

General enquires

browse map
You can contact us directly
open the contact form