Production report about works performed for Dnister Pumped Storage Hydroelectric Power Plant – June 2021

Agreement No. 01-10/2017 dated May 10, 2018 "Building works on the construction of the second stage of Dnistrovska PSPP consisting of the hydroelectric unit No. 4 of the branch "Directorate of Dnistrovska PSPP construction" of PJSC "Ukrhydroenergo"

Works have been completed in full scope:

–  on the installation of lighting for the technology block (1st and
2nd floors) and individual tests (72 hours) have been carried out,
–  on the installation of accumulator battery,
–  on the installation of vibration monitoring system sensors for the hydroelectric unit No. 4 in the presence of UNIX CZ s.r.o. representative;

Construction and installation works are ongoing:

– on the installation of lighting for the hydroelectric unit compartment No.4 (ShGA No. 4),
–  on the installation of lighting for turbine room,
–  on the installation of lighting for the technology block (basement),
–  on the installation of control and power cable lines in the hydroelectric unit compartment No. 4, technology block, PSPP building.

or use keyboard

Kyiv Energy Construction Company Kyiv Energy Construction Company is a leading Ukrainian company providing engineering, procurement and construction (EPC) services for large-scale energy and industrial objects.

Ознайомтеся з іншими новинами

all news
or use keyboard
Contact us
all contacts
Kyiv, Ukraine

01013, 4A Promyslova Str.

(044) 545-71-24

General enquires

mail@kebk.com.ua

General enquires

browse map
You can contact us directly
open the contact form