Works have been completed in full scope:
– on the installation of lighting for the technology block (1st and
2nd floors) and individual tests (72 hours) have been carried out,
– on the installation of accumulator battery,
– on the installation of vibration monitoring system sensors for the hydroelectric unit No. 4 in the presence of UNIX CZ s.r.o. representative;
Construction and installation works are ongoing:
– on the installation of lighting for the hydroelectric unit compartment No.4 (ShGA No. 4),
– on the installation of lighting for turbine room,
– on the installation of lighting for the technology block (basement),
– on the installation of control and power cable lines in the hydroelectric unit compartment No. 4, technology block, PSPP building.