According to the Agreement No. 01-10/2017 dated May 10, 2018 “Building works on the construction of the second stage of Dnistrovska PSPP consisting of the hydroelectric unit No. 4 of the branch “Directorate of Dnistrovska PSPP construction” of PJSC “Ukrhydroenergo” the following works have been
performed:
1. Works have been completed in a full scope:
– on the installation of machine hall lighting;
– on the installation of rigid bus arrangement of current-limiting reactors
according to the corrected design.
2. Construction and installation works are ongoing:
– on the installation of 6 kV cable line “6,3kV metal-clad switchgear-сompressor building of the synchronous compensator No.2 mode”;
– on the installation of lighting of water outlet and gallery of process water supply No.5;
– on the installation and connection of control and power cable lines of ventilation equipment and fire-fighting automatic equipment in hydroelectric unit compartment No.4, technological premise, PSPP building;
– on the installation of external lightning of the technological site, perimeter security lighting;
– on the installation of power cable for heating the technological building gutters;
– on the installation of power supply to the emergency exit compartment No.2.