The signed contract provides for the performance of a full set of design and survey works of the Basic Design and Detail Design phases, as follows:
4.Passing a comprehensive examination of design estimate documentation and receiving a positive expert report.
5.Performance of a full set of design works for the following facilities, the construction of which is assumed in accordance with the Design Assignment:
– reconstruction with the expansion of existing 330kV outdoor switchgear at Rivne NPP;
– construction of a new 330/10 kV substation with indoor 330kV gas insulated switchgear (GIS), with installation of four 330/10/10 kV transformers with a capacity of 80 MVA each, with installation of 10kV metal-clad switchgear;
– laying of two new 330 kV cable lines from 330 kV outdoor switchgear to a new 330/10 kV substation. The total length of each line is 1,5 km;
– arrangement of the power supply circuits for the server equipment of data processing centers (DPC) from new 330/10 kV substation;
– construction of data processing centers on three separate plots, including the technological buildings for the placement of DPC’s server equipment and the arrangement of all necessary utilities and networks.
The completion of all work under the contract is scheduled for August 2022.