According to the Agreement No.01-10/2017 dated May 10, 2018 “Building works on construction of the second stage of the Dnistrovska PSPP consisting of the hydroelectric unit No.4 of the branch “Directorate of Dnistrovska PSPP construction” of “Ukrgidroenergo” PJSC”, the following works have been performed:
The works have been performed in a full scope:
– installation of a cable trays made from “PROMATECT-L500” fireproof slabs in 330kV GIS premises,
– installation of cable trays made from galvanized steel in the continuation of the existing rout on the retaining wall along the turbine room up to axis 54,
Ongoing construction and Installation works:
– installation of lighting for hydroelectric unit compartment №4 (SHGA №4),
– installation of lighting for turbine room,
– installation of cable steel structures in hydroelectric unit compartment №4,
– installation of control and power cable lines in hydroelectric unit compartment №4, technology block, PSPP building,
– wiring of cable and wire products.