Production report about works performed for Zaporizhzhia Nuclear Power Station – February 2021

We report about the works performed at the Zaporizhzhia NPP.

According to Contract No.21367/20 dated 03.12.2019, the works on cable routs replacement at hydraulic structures (spray pools) have been completed.

The works on replacement of SB auxiliary packaged transformer substation (KTPVP SB) at power generator unit No.5, according to Contract No.0704/2020 dated 07.04.2020, have been suspended.

Works on replacement of air circuit breakers at 750 kV AIS, according to the Contract No.22223-20 dated 23.07.2020, are ongoing. Commissioning works on the 750 kV L-Dn/1 circuit breaker are ongoing.

Kyiv Energy Construction Company Kyiv Energy Construction Company is a leading Ukrainian company providing engineering, procurement and construction (EPC) services for large-scale energy and industrial objects.

Our news

all news
or use keyboard
Contact us
all contacts
Kyiv, Ukraine

01013, 4A Promyslova Str.

(044) 545-71-24

General enquires

mail@kebk.com.ua

General enquires

browse map
You can contact us directly
open the contact form