– We installed a double circuit cable line section from the substation building (cable cellar of the 110 kV GIS premises) to 110 kV overhead line (100 kV dead-end anchor tower) with a length of 127 m, with cable fixing in the trench, on supporting structures and the 110 kV tower.
– Cable metal structures for laying of 22 kV cable have been installed.
Kyiv Energy Construction Company Kyiv Energy Construction Company is a leading Ukrainian company providing engineering, procurement and construction (EPC) services for large-scale energy and industrial objects.